Glassford Hill Road Widening Project Update | Oct 19th - 23rd, 2026
Send us a text and chime in! Roadway and Wall Construction Ongoing Along Glassford Hill Road Crews continue with roadway excavation, subgrade preparation, retaining wall construction and the installation of curb, gutter and sidewalk along Glassford Hill Road, from Spouse Drive to just north of Tuscany Way/Granville Parkway, throughout the week. Please be aware of the following impacts: Monday, October 19 through Friday, October 23, 7 a.m. – 7 p.m. Road users are advised to be alert, use cauti...