Glassford Hill Road Widening Project Update | Jun 8th - 12th, 2026
Episode 2 min

Glassford Hill Road Widening Project Update | Jun 8th - 12th, 2026

Send us a text and chime in! Final Round of Asphalt Paving to Begin in First Phase Crews will be performing the final round of asphalt paving within the first phase of work along Glassford Hill Road, from just north of Long Look Drive to just south of Spouse Drive. Following the completion of paving operations, roadway striping will occur. Please be aware of the following impacts: Monday, June 8 through Friday, June 12, 7 a.m. – 7 p.m., One lane of traffic in each direction of Glassford Hill ...